600 Ortega St
San Francisco permit 202506138686 · Inner Sunset
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa# 202304276609, ref planning 2024-007542prj, add an elevator penthouse, service roof deck, and exterior spiral staircase. the elevator penthouse will be approximately 12 feet in height.
- Filed
- Jun 27, 2025
- Issued
- Nov 6, 2025 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 19 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 12, 2025 | Jun 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2025 | Jul 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 1, 2025 | Jul 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2025 | Oct 14, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2025 | Aug 22, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2025 | Aug 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 1, 2025 | Jul 8, 2025 | Issued Comments |
Building inspector Building Inspection · BID-INSP | Jul 1, 2025 | Oct 20, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 1, 2025 | Oct 28, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 5, 2025 | Aug 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 20, 2025 | Aug 20, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 5, 2025 | Sep 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 3, 2025 | Oct 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 9, 2025 | Oct 9, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 14, 2025 | Oct 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 14, 2025 | Oct 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 14, 2025 | Oct 14, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Oct 14, 2025 | Oct 15, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2025 | Nov 6, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $57,394
| Name | Role | License on permit |
|---|---|---|
| Geoffrey Gibson Winder Gison Architects | Architect | C35924 |
| Jason Allen Pisano Hom Pisano Engineering Inc | Engineer | 69708 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2015