As written on the permit application.

Convert (e) bedroom, workroom and laundry into a (n) adu and add (n) kitchen

Timeline
Key dates from the city record.
Filed
Feb 2, 2026
Issued
May 1, 2026 (3 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
20 stops across 6 departments
Comments issued
5 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 27, 2025Issued Comments

Central Permit Bureau

Building Inspection · CPB

Feb 19, 2026Administrative

Permit Center

Permit Center · PERMIT-CTR

Jul 25, 2025Approved

Permit Processing Center

Building Inspection · PPC

Apr 15, 2026Administrative

Zoning review

Planning · CP-ZOC

Mar 11, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Mar 5, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 4, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 5, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 24, 2026Approved

Urban forestry

Public Works · DPW-BUF

Mar 9, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 4, 2026Approved

Zoning review

Planning · CP-ZOC

Mar 16, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 17, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 16, 2026Approved

Fire prevention review

Fire Department · SFFD

Mar 20, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Mar 18, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 7, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 31, 2026Approved

Fire prevention review

Fire Department · SFFD

Mar 23, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 1, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$50,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
L A Paul

L.A. Paul & Assoc.

ArchitectC-8725
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202506168790 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record