442 Wilde Av
San Francisco permit 202506168793 · Visitacion Valley
Converting (e) udu at lower lvl of bldg to adu. proposed adu consists of living/dining area, 1-bedroom, 1-bath and a kitchen that has been converted from a laundry. total adu area is 1,068 sqft.
- Filed
- Jul 23, 2025
- Issued
- Jul 21, 2026 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 49 stops across 6 departments
- Comments issued
- 10 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 13, 2025 | Jun 27, 2025 | Issued Comments |
Apartment and hotel inspection Building Inspection · HIS | Jun 17, 2025 | Jun 17, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jul 11, 2025 | Jul 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2025 | Jul 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 24, 2025 | Jul 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 24, 2025 | Aug 18, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 24, 2025 | Aug 18, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 24, 2025 | Aug 8, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 24, 2025 | Jul 25, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2025 | Jul 30, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 24, 2025 | Aug 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 24, 2025 | Aug 1, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 24, 2025 | Mar 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 5, 2025 | Oct 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 5, 2025 | Sep 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 5, 2025 | Sep 8, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Sep 5, 2025 | Sep 9, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 5, 2025 | Sep 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 5, 2025 | Sep 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 5, 2025 | Sep 9, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 31, 2025 | Nov 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 31, 2025 | Nov 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2025 | Nov 4, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 31, 2025 | Nov 6, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2025 | Nov 4, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 31, 2025 | Nov 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2025 | Nov 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 6, 2025 | Dec 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2025 | Nov 18, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Nov 6, 2025 | Nov 7, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Nov 6, 2025 | Nov 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2025 | Nov 14, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Dec 18, 2025 | Dec 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 7, 2026 | Jan 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 7, 2026 | Jan 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2026 | Jan 12, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jan 7, 2026 | Jan 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 7, 2026 | Jan 8, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 7, 2026 | Jan 26, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2026 | Jan 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 9, 2026 | Feb 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Feb 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 9, 2026 | Feb 19, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Feb 9, 2026 | Feb 11, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2026 | Feb 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 9, 2026 | Mar 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2026 | Feb 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Jul 21, 2026 | Administrative |
Address verification Building Inspection · ADDR | Jul 10, 2026 | Jul 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $40,000
| Name | Role | License on permit |
|---|---|---|
| Derrick T Wu Derrick T Wu Architect | Architect | C23451 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025