1369 26th Av
San Francisco permit 202506178853 · Sunset/Parkside
Legalize (e) 1/f unt per nov202293112 & 202293060.remove (e) stair btwn 1/f -2/f; relocate (e) unit entry;reconfig (e) kitchen;relocate (e) bath,provide 1h p|l & passageway to new adu & 1h sep to adj unit/garage/storage areas.provision f/s at unit and to entry under sep permit.
- Filed
- Aug 6, 2025
- Issued
- Jan 28, 2026 (6 months after filing)
- Completed
- Jun 30, 2026 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 28 stops across 6 departments
- Comments issued
- 8 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 16, 2025 | Jun 30, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 24, 2025 | Aug 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 7, 2025 | Aug 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 7, 2025 | Sep 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 7, 2025 | Aug 26, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 7, 2025 | Aug 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 7, 2025 | Aug 22, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 7, 2025 | Aug 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 7, 2025 | Aug 12, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 7, 2025 | Sep 29, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 7, 2025 | Aug 12, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 7, 2025 | Dec 10, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Aug 14, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 1, 2025 | Oct 2, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 1, 2025 | Nov 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 1, 2025 | Oct 8, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 1, 2025 | Oct 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 1, 2025 | Oct 6, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 1, 2025 | Oct 8, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2025 | Oct 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 23, 2025 | Dec 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2025 | Oct 27, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 23, 2025 | Nov 12, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2025 | Oct 27, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 23, 2025 | Nov 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2025 | Oct 27, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Dec 10, 2025 | Dec 10, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 10, 2025 | Jan 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $159,065
| Name | Role | License on permit |
|---|---|---|
| Roberta A Wahl Plum Architects | Architect | C28322 |
| Albert Urrutia Atrium Structural Engineering | Engineer | S-2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023