401 California Av
San Francisco permit 202506209120 · Treasure Island
To erect 6 stories, no basement, type i-a & ii-a, 150 units residential units with child development center (warmshell), (r-2, b,a-3,s-1,s-2,i-4)
- Filed
- Jul 15, 2025
- Issued
- Jul 1, 2026 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 79 stops across 7 departments
- Comments issued
- 20 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Health, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 21, 2025 | Jul 15, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jun 11, 2025 | Jun 27, 2025 | Issued Comments |
Apartment and hotel inspection Building Inspection · HIS | Jun 24, 2025 | Jun 24, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jul 10, 2025 | Jul 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 15, 2025 | Jul 29, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 15, 2025 | Aug 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 15, 2025 | Jul 30, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2025 | Jul 22, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 15, 2025 | Sep 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2025 | Jul 29, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 15, 2025 | Aug 1, 2025 | Approved |
Public Health HEALTH-MH | Jul 15, 2025 | Jul 18, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 15, 2025 | May 8, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Aug 21, 2025 | Aug 25, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 5, 2025 | Dec 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2025 | Jan 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 5, 2025 | Dec 23, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2025 | Dec 17, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Dec 5, 2025 | Dec 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2025 | Dec 9, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 5, 2025 | Dec 12, 2025 | Approved |
Public Health HEALTH-MH | Dec 5, 2025 | Dec 9, 2025 | Issued Comments |
Public Health HEALTH-MH | Jan 5, 2026 | Jan 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 6, 2026 | Apr 8, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 9, 2026 | Apr 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 14, 2026 | Apr 14, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2026 | Apr 22, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 14, 2026 | Apr 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2026 | Apr 24, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 14, 2026 | Apr 17, 2026 | Approved |
Public Health HEALTH-MH | Apr 14, 2026 | Apr 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 30, 2026 | Apr 30, 2026 | Approved-Stipulated |
Address verification Building Inspection · ADDR | May 5, 2026 | May 5, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | May 5, 2026 | May 5, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 8, 2026 | Jul 1, 2026 | Administrative |
Addendum 1: Excavation, grading, below grade utilities (including civil, underground mep)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 30, 2025 | Aug 11, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jul 25, 2026 | Aug 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 11, 2026 | Sep 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 11, 2026 | Sep 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2026 | Aug 24, 2026 | Issued Comments |
Public Health HEALTH-MH | Aug 11, 2026 | Aug 19, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 11, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Oct 28, 2026 | Oct 28, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2026 | Nov 4, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Nov 4, 2026 | In progress | — |
Public Health HEALTH-MH | Nov 4, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 2: Structural (foundation, podium, superstructure / framing)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 25, 2026 | Aug 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2026 | Aug 11, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 11, 2026 | Oct 8, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 11, 2026 | Oct 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 11, 2026 | Sep 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2026 | Aug 24, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 11, 2026 | Sep 29, 2026 | Approved |
Public Health HEALTH-MH | Aug 11, 2026 | Sep 21, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 11, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Architectural, landscape, irrigation, t-24, mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 25, 2026 | Aug 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 3, 2026 | Aug 17, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 17, 2026 | Aug 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 17, 2026 | Oct 15, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2026 | Aug 28, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 17, 2026 | Oct 9, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 17, 2026 | Sep 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 17, 2026 | Aug 24, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 17, 2026 | Sep 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2026 | Aug 18, 2026 | Approved |
Public Health HEALTH-MH | Aug 17, 2026 | Aug 19, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 17, 2026 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Oct 8, 2026 | Oct 14, 2026 | Administrative |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $79,391,871
| Name | Role | License on permit |
|---|---|---|
| Paulett Long Taggart Paulett Taggart Architects | Architect | C10957 |
| Joseph Mccue M B H | Engineer | C74959 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2019