CheckMyDesigner

422 Funston Av

San Francisco permit 202506249351 · Inner Richmond

ADUFull plan reviewComplete
Street view · Sep 2026
Google Street View of 422 Funston Av, Sep 2026
Scope of work
As written on the permit application.

Addition of adu located at ground floor to be submitted under state program . adu to be studio apartment (total 630sf) seismic upgrade to 1st floor.

Timeline
Key dates from the city record.
Filed
Jul 7, 2025
Issued
Sep 16, 2025 (2 months after filing)
Completed
Jun 9, 2026 (9 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
21 stops across 6 departments
Comments issued
5 times, by Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 2, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 7, 2025Administrative

Zoning review

Planning · CP-ZOC

Aug 19, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 29, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 29, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 29, 2025Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Jul 9, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 9, 2025Approved

Urban forestry

Public Works · DPW-BUF

Aug 8, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 9, 2025Approved

Permit Processing Center

Building Inspection · PPC

Sep 8, 2025Administrative

Fire Department housing review

Fire Department · SFFD-HQ

Aug 13, 2025Approved-Stipulated

Mechanical and energy plan review

Building Inspection · MECH

Aug 15, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 21, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 20, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 21, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 25, 2025Approved

Urban forestry

Public Works · DPW-BUF

Sep 2, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 29, 2025Approved

Development fee collection

Building Inspection · DFCU

Sep 2, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Sep 16, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$120,300
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Katherine Ann Fontaine

Actually Design Build

ArchitectC34740
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202506249351 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record