249 Peru Av
San Francisco permit 202506249368 · Excelsior
Remove rear portion of the building, excavate crawl space and grade at rear yard to create new basement, new interior stairs connecting 1st floor with basement; horizontal addition at rear yard for 1st floor and basement, relocate kitchen and bathroom in first floor; new window and exterior doors.
- Filed
- Dec 13, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 6 departments
- Comments issued
- 5 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 20, 2025 | Jul 2, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 21, 2025 | Dec 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 8, 2025 | Dec 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 15, 2025 | Dec 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 15, 2025 | Dec 23, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 15, 2025 | Dec 23, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2025 | Jan 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Dec 15, 2025 | Dec 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2025 | Dec 16, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 15, 2025 | Dec 22, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2025 | Dec 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 15, 2025 | Jan 29, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2026 | Jan 16, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 9, 2026 | Jan 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2026 | Jan 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 12, 2026 | Jan 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2026 | Jan 12, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 14, 2026 | Jan 15, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 16, 2026 | Jan 21, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 16, 2026 | Jan 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 29, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $325,000
| Name | Role | License on permit |
|---|---|---|
| Jorge R Carbonell Jorge Carbonell Architecture | Architect | C30680 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
| Erwin J O'toole Erwin O'toole | Engineer | C80734 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019