229 Whitney St
San Francisco permit 202506249375 · Glen Park
Construct 3-story & 1 basement: 3-residentail units and attached 1-state adu, type 5b, apprx. 4700 gross square feet
- Filed
- Oct 29, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 28 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 18, 2025 | Jul 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2025 | Dec 31, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 31, 2025 | Jan 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 31, 2025 | Feb 12, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Dec 31, 2025 | Jan 21, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2025 | Jan 5, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Dec 31, 2025 | Jan 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 31, 2025 | Jan 2, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 31, 2025 | Jan 9, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 31, 2025 | Sep 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 17, 2026 | Jul 20, 2026 | Approved |
Address verification Building Inspection · ADDR | Jul 17, 2026 | Jul 27, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 17, 2026 | Jul 20, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jul 17, 2026 | Jul 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2026 | Jul 20, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 17, 2026 | Aug 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 17, 2026 | Jul 28, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 17, 2026 | Jul 31, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2026 | Aug 18, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 14, 2026 | Aug 14, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 18, 2026 | Aug 20, 2026 | Approved |
Address verification Building Inspection · ADDR | Aug 18, 2026 | Aug 20, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Aug 18, 2026 | Aug 18, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 18, 2026 | Aug 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2026 | Aug 20, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 18, 2026 | Aug 25, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Aug 25, 2026 | Aug 26, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Filed
- Estimated cost
- $1,500,000
| Name | Role | License on permit |
|---|---|---|
| Martin C Kellogg | Architect | C35171 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025