451 Anderson St
San Francisco permit 202506259459 · Bernal Heights
Horizontal addition at back of house at 1st & 2nd floor & remodel interior stairway. add new skylights in (e) living area & (e) bedroom.
- Filed
- Aug 6, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 34 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 23, 2025 | Jul 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2025 | Aug 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 6, 2025 | Aug 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 6, 2025 | Sep 16, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 6, 2025 | Sep 8, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Aug 6, 2025 | Sep 4, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 6, 2025 | Aug 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2025 | Aug 14, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 6, 2025 | Sep 3, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2025 | Aug 12, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 6, 2025 | Jun 17, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Jan 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Mar 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Jan 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Jan 22, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 21, 2026 | Feb 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Jan 27, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 18, 2026 | May 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 18, 2026 | May 29, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 18, 2026 | May 19, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 18, 2026 | May 20, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 18, 2026 | May 20, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 18, 2026 | Jun 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 18, 2026 | May 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 20, 2026 | May 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 27, 2026 | Jun 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2026 | Jun 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 27, 2026 | Jun 1, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 27, 2026 | May 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 27, 2026 | Jun 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 27, 2026 | Jun 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 1, 2026 | Jun 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Marc A Lindsell 2m Architecture | Architect | C25915 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023