CheckMyDesigner

173 Downey St

San Francisco permit 202506259462 · Haight Ashbury

Home remodelFull plan reviewIssued
Street view · Jan 2023
Google Street View of 173 Downey St, Jan 2023
Scope of work
As written on the permit application.

Renovate kitchen. renovate 3 bathrooms. add (1) new bathroom on 3/f and (1) half bath on 2/f. new elevator, new radiant heating at all 3 floors. new air conditioning at 3/f.

Timeline
Key dates from the city record.
Filed
Jul 31, 2025
Issued
Dec 8, 2025 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 5 departments
Comments issued
8 times, by Building Inspection, Fire Department
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Jun 25, 2025Administrative

Zoning review

Planning · CP-ZOC

Jun 25, 2025Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Jul 18, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 31, 2025Administrative

Building plan review

Building Inspection · BLDG

Aug 27, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 3, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 29, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 5, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 7, 2025Approved

Permit Processing Center

Building Inspection · PPC

Nov 21, 2025Administrative

Building plan review quality control

Building Inspection · BLDG-QC

Aug 27, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 22, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 14, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 24, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 2, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 9, 2025Approved-Stipulated

Structural plan approval

Building Inspection · PAD-STR

Oct 20, 2025Approved

Fire prevention review

Fire Department · SFFD

Oct 22, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Oct 27, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 4, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 7, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 18, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 19, 2025—

Fire prevention review

Fire Department · SFFD

Nov 19, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Nov 21, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 8, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$629,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
David Edward Cumby

Cumby Architecture

ArchitectC29182
Donald David

Double D Engineering

EngineerS3928
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202506259462 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record