42 Allen St
San Francisco permit 202506309753 · Russian Hill
A mandatory seismic upgrade unconditioned garage of ab-106 and ab-107. conversion of(e)unconditioned garage & storage spaces into 2 adu & utility room in the(e)3 level multi-family building as indicated on drawings.demolition of the(e)storage rooms in the rear yard.
- Filed
- Jul 18, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 29 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 27, 2025 | Jul 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2025 | Jul 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 21, 2025 | Jul 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 21, 2025 | Aug 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 21, 2025 | Aug 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2025 | Aug 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 21, 2025 | Aug 6, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2025 | Jul 23, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 21, 2025 | Aug 22, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2025 | Jul 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 21, 2025 | In progress | — |
Zoning review Planning · CP-ZOC | Oct 24, 2025 | Oct 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2025 | Oct 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 27, 2025 | Oct 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 29, 2025 | Oct 29, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 3, 2025 | Nov 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 4, 2025 | Nov 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 10, 2025 | Nov 10, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 1, 2025 | Dec 1, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 1, 2025 | Dec 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 3, 2025 | Dec 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 5, 2025 | Dec 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 9, 2025 | Dec 9, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 10, 2025 | Dec 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 21, 2026 | Apr 21, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $507,486
| Name | Role | License on permit |
|---|---|---|
| Mahya Salehi Fadardi | Architect | C38610 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025