364 Moscow St
San Francisco permit 202507019897 · Excelsior
Rebuild exterior entry stairs to bring into compliance. new front facade windows, withing (e) window openings. new exterior swing door for garage level. no change to (e) garage door or (e) entry door. replace with (e) opening single winodw on south side facade.
- Filed
- Jul 1, 2025
- Issued
- Jan 21, 2026 (7 months after filing)
- Completed
- May 29, 2026 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 10 stops across 2 departments
- Comments issued
- Once, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 1, 2025 | Jul 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 1, 2025 | Jul 1, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 10, 2025 | Jul 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 10, 2025 | Jul 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 10, 2025 | Jul 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 4, 2025 | Nov 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 4, 2025 | Nov 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 4, 2025 | Nov 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Jan 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2026 | Jan 21, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $20,000
| Name | Role | License on permit |
|---|---|---|
| Audrey A Bauer Studio Maven | Architect | C36620 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019