1269 05th Av

San Francisco permit 202507020073 · Inner Sunset

AdditionFull plan reviewIssued
Street view · Mar 2022
Google Street View of 1269 05th Av, Mar 2022
Scope of work
As written on the permit application.

Remodel of 2 unit bldg with 450 squre foot additon at 1st and 2nd floor(unit 1269) and 94 square foot additon at 3rd floor(unit 1271)

Timeline
Key dates from the city record.
Filed
Jul 15, 2025
Issued
Nov 26, 2025 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 6 departments
Comments issued
7 times, by Building Inspection, Fire Department, Public Works, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 11, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 16, 2025Administrative

Zoning review

Planning · CP-ZOC

Jul 17, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 18, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 5, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 8, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 17, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 17, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Aug 8, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 17, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Nov 10, 2025Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Jul 24, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Aug 18, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Sep 24, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Oct 2, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 26, 2025Approved-Stipulated

Mechanical and energy plan review

Building Inspection · MECH

Sep 29, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 21, 2025Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Oct 21, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 27, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Oct 29, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 28, 2025Approved

Fire prevention review

Fire Department · SFFD

Oct 28, 2025Approved-Stipulated

Zoning review

Planning · CP-ZOC

Oct 30, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 3, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 3, 2025Approved

Urban forestry

Public Works · DPW-BUF

Nov 7, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 26, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$833,360
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Antje Paiz

Raumfabrick Architecture

ArchitectC31989
Peter David Bonneau

Pe Structural Design

EngineerC81545
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202507020073 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record