1935 Webster St
San Francisco permit 202507030118 · Pacific Heights
Rear horizontal additions at lvls 1 and 2. interior remodel @ lvls 1, 2 & 3 to include reconfiguring of the floor plan layouts at all levels. (n) rear roof deck at lvl 2. new windows and siding at rear, & replacement of (e) window sashes at front and side facades.
- Filed
- Jul 10, 2025
- Issued
- Dec 24, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 7 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 1, 2025 | Jul 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2025 | Jul 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 10, 2025 | Jul 15, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 10, 2025 | Sep 10, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 10, 2025 | Aug 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 10, 2025 | Jul 29, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 10, 2025 | Jul 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2025 | Jul 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 10, 2025 | Jul 11, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 10, 2025 | Nov 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 29, 2025 | Sep 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 29, 2025 | Oct 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 29, 2025 | Oct 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 29, 2025 | Oct 6, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 29, 2025 | Sep 30, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 29, 2025 | Oct 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 29, 2025 | Oct 3, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Oct 15, 2025 | Oct 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 3, 2025 | Nov 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 3, 2025 | Nov 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2025 | Nov 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 3, 2025 | Nov 13, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 3, 2025 | Nov 6, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2025 | Nov 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2025 | Nov 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 13, 2025 | Dec 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,290,580
| Name | Role | License on permit |
|---|---|---|
| Kelly D Melendez Kelly Melendez Architect | Architect | C27652 |
| Doug Lee Doug Lee | Engineer | C74001 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025