CheckMyDesigner

1935 Webster St

San Francisco permit 202507030118 · Pacific Heights

AdditionFull plan reviewIssued
Street view · Jun 2025
Google Street View of 1935 Webster St, Jun 2025
Scope of work
As written on the permit application.

Rear horizontal additions at lvls 1 and 2. interior remodel @ lvls 1, 2 & 3 to include reconfiguring of the floor plan layouts at all levels. (n) rear roof deck at lvl 2. new windows and siding at rear, & replacement of (e) window sashes at front and side facades.

Timeline
Key dates from the city record.
Filed
Jul 10, 2025
Issued
Dec 24, 2025 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 6 departments
Comments issued
7 times, by Planning, Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 10, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 10, 2025Administrative

Zoning review

Planning · CP-ZOC

Jul 15, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Sep 10, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 26, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 29, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 15, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 14, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 11, 2025Approved

Permit Processing Center

Building Inspection · PPC

Nov 13, 2025Administrative

Zoning review

Planning · CP-ZOC

Sep 29, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 15, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 9, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 6, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 30, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 2, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 3, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Oct 15, 2025Approved

Zoning review

Planning · CP-ZOC

Nov 3, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 13, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 7, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 13, 2025Approved

Fire prevention review

Fire Department · SFFD

Nov 6, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Nov 5, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 4, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 24, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,290,580
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Kelly D Melendez

Kelly Melendez Architect

ArchitectC27652
Doug Lee

Doug Lee

EngineerC74001
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202507030118 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record