311 A Vienna St
San Francisco permit 202507030143 · Excelsior
State adu program- convert garage space into adu.
- Filed
- Jul 28, 2025
- Issued
- Mar 30, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 39 stops across 6 departments
- Comments issued
- 13 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 2, 2025 | Jul 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2025 | Jul 29, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 29, 2025 | Aug 11, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 29, 2025 | Jul 31, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 29, 2025 | Aug 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 29, 2025 | Aug 6, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 29, 2025 | Jul 30, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 29, 2025 | Jul 30, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 29, 2025 | Aug 11, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 29, 2025 | Aug 1, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 29, 2025 | Mar 26, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Nov 12, 2025 | Nov 13, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 12, 2025 | Nov 13, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 12, 2025 | Nov 23, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 12, 2025 | Nov 20, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Nov 12, 2025 | Nov 13, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2025 | Nov 13, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 12, 2025 | Nov 21, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2025 | Nov 19, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 23, 2025 | Dec 30, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 23, 2025 | Dec 31, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 23, 2025 | Dec 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2025 | Dec 31, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Dec 23, 2025 | Dec 24, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2025 | Dec 26, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 23, 2025 | Dec 31, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2025 | Dec 24, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jan 7, 2026 | Jan 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 30, 2026 | Jan 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2026 | Feb 5, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 30, 2026 | Feb 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2026 | Feb 17, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jan 30, 2026 | Feb 2, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2026 | Feb 3, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 30, 2026 | Feb 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2026 | Feb 3, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Feb 17, 2026 | Feb 17, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 24, 2026 | Mar 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2026 | Mar 30, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $204,157
| Name | Role | License on permit |
|---|---|---|
| Grace Harter O'rourke Adapt Dwellings | Architect | C-37272 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025