255 Winston Dr
San Francisco permit 202507030201 · Lakeshore
Sign 12: install (1) new 10" x 3'6" x 6'6" canopy and (1) new cove lighting. sign 13: canopy site specific
- Filed
- Jul 3, 2025
- Issued
- Aug 7, 2026 (13 months after filing)
- Completed
- Oct 20, 2026 (2 months after issuance)
- Review stops
- 17 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 3, 2025 | Jul 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 3, 2025 | Jul 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 3, 2025 | Jul 3, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Jan 27, 2026 | Jan 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 27, 2026 | Jan 27, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 27, 2026 | Jan 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 27, 2026 | Jan 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 27, 2026 | Jan 27, 2026 | Approved |
Intake Building Inspection · INTAKE | Mar 9, 2026 | Mar 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 9, 2026 | Mar 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 17, 2026 | Mar 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 17, 2026 | Mar 17, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | May 15, 2026 | Jul 31, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 15, 2026 | May 15, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 24, 2026 | Jul 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2026 | Jul 31, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 7, 2026 | Aug 7, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $30,000
| Name | Role | License on permit |
|---|---|---|
| Brett Sauers Reverence Engineering | Engineer | C81435 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022