331 Cortland Av
San Francisco permit 202507080388 · Bernal Heights
Permit for removal of kitchen and walls by previous owner in order to use the approved cua. 331 cortland, existing b occupancy, will be used for religious services, 333 cortland, a vacant unit with r-3 occupancy, will be used for admin uses with the b occupancy. rear building: 331a cortland is r-3
- Filed
- Jul 8, 2025
- Issued
- Aug 14, 2025 (1 month after filing)
- Completed
- Dec 22, 2025 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building pre-screening Building Inspection · PRE-BLDG | Jul 8, 2025 | Jul 8, 2025 | Approved |
Intake Building Inspection · INTAKE | Jul 8, 2025 | Jul 8, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 8, 2025 | Jul 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 8, 2025 | Jul 8, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2025 | Jul 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 9, 2025 | Jul 9, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 9, 2025 | Jul 9, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Jul 9, 2025 | Jul 9, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jul 9, 2025 | Jul 9, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 13, 2025 | Aug 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2025 | Aug 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $10,000
| Name | Role | License on permit |
|---|---|---|
| Steven H Rajninger Locus Architecture | Architect | C-26170 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2009