San Francisco permit 202507090404 · Treasure Island

New buildingFull plan reviewIssued
Street view · Mar 2025
Google Street View of 150 04th Ti St, Mar 2025
Scope of work
As written on the permit application.

Priority 100% affortable project - erect a 5-story, no basement, type ii-a, 100 units of affordable senior housing with associated community and management spaces. (r-2,s-2,b)

Timeline
Key dates from the city record.
Filed
Jul 14, 2025
Issued
Jan 5, 2026 (6 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
89 stops across 7 departments
Comments issued
20 times, by Building Inspection, Fire Department, Public Utilities, Permit Center, Public Works, Public Health

Main permit

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 11, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 14, 2025Administrative

Zoning review

Planning · CP-ZOC

Sep 8, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 6, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 21, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 15, 2025Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Aug 28, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 1, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Jul 25, 2025Approved

Public Health

HEALTH-MH

Jul 18, 2025Approved

Permit Processing Center

Building Inspection · PPC

Dec 11, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 28, 2025Approved

Building plan review

Building Inspection · BLDG

Sep 22, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 11, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 11, 2025Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Sep 22, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 11, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Sep 11, 2025Approved

Public Health

HEALTH-MH

Sep 17, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Sep 22, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 13, 2025Approved

Fire prevention review

Fire Department · SFFD

Nov 3, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 3, 2025Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Nov 7, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 10, 2025Issued Comments

Public Utilities programs review

Public Utilities · SFPUC-PRG

Nov 4, 2025Approved

Public Health

HEALTH-MH

Oct 28, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 13, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Nov 14, 2025Approved

Zoning review

Planning · CP-ZOC

Nov 21, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 25, 2025Approved

Fire prevention review

Fire Department · SFFD

Dec 4, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Nov 25, 2025Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Nov 24, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 3, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Dec 1, 2025Approved

Public Health

HEALTH-MH

Nov 25, 2025Approved

Development fee collection

Building Inspection · DFCU

Dec 5, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Jan 5, 2026Administrative

Addendum 1: Foundation, concrete superstructure & underground utilities

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 27, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Mar 16, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Mar 16, 2026Administrative

Building plan review

Building Inspection · BLDG

Apr 13, 2026Administrative

Structural plan approval

Building Inspection · PAD-STR

Apr 24, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Mar 30, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 23, 2026Issued Comments

Public Health

HEALTH-MH

Mar 27, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

Sep 23, 2026Administrative

Structural plan approval

Building Inspection · PAD-STR

Jun 5, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Jun 1, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Jun 1, 2026Issued Comments

Public Health

HEALTH-MH

Jun 1, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 25, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Jun 25, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Jun 26, 2026Approved-Stipulated

Public Health

HEALTH-MH

Jun 17, 2026Approved

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Addendum 2: Steel framed superstructure

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 27, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 28, 2026Administrative

Building plan review

Building Inspection · BLDG

Jul 17, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 29, 2026Administrative

Fire Department housing review

Fire Department · SFFD-HQ

Jun 8, 2026Not Applicable

Street use and mapping

Public Works · DPW-BSM

Jun 24, 2026Issued Comments

Public Health

HEALTH-MH

Jun 1, 2026Not Applicable

Permit Processing Center

Building Inspection · PPC

Oct 7, 2026Administrative

Building plan review

Building Inspection · BLDG

Oct 7, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Sep 28, 2026Not Applicable

Street use and mapping

Public Works · DPW-BSM

Sep 28, 2026Not Applicable

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Addendum 3: Architectural. landscape and civil

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 11, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jul 1, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jul 2, 2026Administrative

Zoning review

Planning · CP-ZOC

Jul 6, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 21, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 17, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Jul 22, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 16, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 10, 2026Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Jul 8, 2026Approved

Plumbing plan check

Building Inspection · PID-PC

Jul 9, 2026Issued Comments

Public Health

HEALTH-MH

Jul 7, 2026Approved

Permit Processing Center

Building Inspection · PPC

In progress—

Building plan review quality control

Building Inspection · BLDG-QC

Aug 21, 2026Administrative

Building plan review

Building Inspection · BLDG

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Fire Department housing review

Fire Department · SFFD-HQ

In progress—

Street use and mapping

Public Works · DPW-BSM

In progress—

Plumbing plan check

Building Inspection · PID-PC

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Issued
Estimated cost
$40,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Bruce Christian Prescott

Santos Prescott & Assoc.

ArchitectC23687
Jacqueline Lingwei Luk

Luk And Associates

EngineerC75724
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202507090404 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record