240 Upland Dr
San Francisco permit 202507100538 · West of Twin Peaks
To comply with dbi-audit nov #202422367. 1/f: enlargement of garage door, addtional excavation to enlarge family room, add one office, front facade window replacement, modification of windows on southeast, northwest and northeast. 2/f: relocate the kitchen, modification of bathroom layout.
- Filed
- Jan 13, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 26 stops across 6 departments
- Comments issued
- 6 times, by Planning, Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 10, 2025 | Jul 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 10, 2025 | Jul 10, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 11, 2025 | Jul 11, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 11, 2025 | Jul 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2025 | Jul 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2025 | Jul 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2025 | Jul 11, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 14, 2025 | Jul 14, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jul 18, 2025 | Aug 1, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jul 21, 2025 | Jan 14, 2026 | Administrative |
Intake Building Inspection · INTAKE | Dec 10, 2025 | Dec 10, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Dec 12, 2025 | Jan 2, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 14, 2026 | Jan 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 14, 2026 | Jan 27, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 14, 2026 | Mar 4, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2026 | Feb 11, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 14, 2026 | Jan 28, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 14, 2026 | Jan 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 14, 2026 | Feb 20, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 14, 2026 | Jan 26, 2026 | Approved |
Building inspector Building Inspection · BID-INSP | Jan 14, 2026 | Feb 2, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 14, 2026 | In progress | — |
Urban forestry Public Works · DPW-BUF | May 15, 2026 | May 15, 2026 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $673,356
| Name | Role | License on permit |
|---|---|---|
| Pezhman Motevaseli Rkd Consulting Inc. | Engineer | C78170 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022