663 02nd Av
San Francisco permit 202507110606 · Inner Richmond
Rear deck remodel and extension with lower (e) hot tub landing. new rear garage man door to replace existing window. no work to building front or interior.
- Filed
- Jul 11, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 13 stops across 4 departments
- Comments issued
- 4 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 11, 2025 | Jul 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 11, 2025 | Jul 11, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 25, 2025 | Nov 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2025 | Dec 2, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 2, 2025 | Dec 2, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Sep 25, 2026 | Sep 25, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 5, 2026 | Oct 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 8, 2026 | Oct 8, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 8, 2026 | Oct 8, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Oct 8, 2026 | Oct 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 8, 2026 | Oct 8, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $26,500
| Name | Role | License on permit |
|---|---|---|
| Sheldon Errol Eaton Vicinity Architects | Architect | C36656 |
| Della Tran Della Tran | Engineer | 91229 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023