210 Lake St
San Francisco permit 202507110673 · Inner Richmond
Construct (n) garage addition above grade. garage addition matches adjacent neighbors (e) build out. interior remodel to bottom unit#212 kitchen, bathrm & common spaces. remodel includes (n) horizontal addition to unit#212 @ rear of house. (n) patio, door & window for unit#210. provide 2 bicycle..
- Filed
- Aug 4, 2025
- Issued
- Jan 16, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 27 stops across 7 departments
- Comments issued
- 8 times, by Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 10, 2025 | Jul 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2025 | Aug 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 5, 2025 | Jan 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 5, 2025 | Sep 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Sep 16, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2025 | Sep 4, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 5, 2025 | Aug 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2025 | Aug 7, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 5, 2025 | Sep 3, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2025 | Aug 7, 2025 | Issued Comments |
Public Health HEALTH-MH | Aug 5, 2025 | Aug 7, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 5, 2025 | Jan 9, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Sep 12, 2025 | Sep 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 31, 2025 | Nov 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 4, 2025 | Dec 12, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 12, 2025 | Nov 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 17, 2025 | Nov 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2025 | Dec 9, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 27, 2025 | Dec 11, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 1, 2025 | Dec 1, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 10, 2025 | Dec 17, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 11, 2025 | Dec 15, 2025 | Approved |
Public Health HEALTH-MH | Dec 11, 2025 | Dec 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2025 | Dec 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 6, 2026 | Jan 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2026 | Jan 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2026 | Jan 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $923,004
| Name | Role | License on permit |
|---|---|---|
| David Townsend Brown Townsend Brown Engineering | Engineer | 74826 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020