1948 Great Hy

San Francisco permit 202507150816 · Sunset/Parkside

ADUFull plan reviewComplete
Street view · May 2022
Google Street View of 1948 Great Hy, May 2022
Scope of work
As written on the permit application.

New 374sf studio converted into adu on g/f of (e) duplex - under state adu. legalize (e) kitchen and bathroom, no layout changes. no exterior changes.

Timeline
Key dates from the city record.
Filed
Aug 20, 2025
Issued
Jan 20, 2026 (5 months after filing)
Completed
Oct 16, 2026 (9 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 6 departments
Comments issued
5 times, by Planning, Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 14, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 20, 2025Administrative

Zoning review

Planning · CP-ZOC

Sep 15, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Sep 2, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 28, 2025Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Aug 29, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 8, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 21, 2025Approved

Urban forestry

Public Works · DPW-BUF

Sep 15, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 3, 2025Approved

Permit Processing Center

Building Inspection · PPC

Dec 10, 2025Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Aug 27, 2025Approved

Zoning review

Planning · CP-ZOC

Dec 2, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Nov 25, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 25, 2025Approved

Fire prevention review

Fire Department · SFFD

Nov 21, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Dec 9, 2025Approved

Urban forestry

Public Works · DPW-BUF

Dec 9, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 1, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Dec 8, 2025Approved

Zoning review

Planning · CP-ZOC

Dec 9, 2025Approved

Development fee collection

Building Inspection · DFCU

Dec 9, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Jan 20, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$158,976
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Joshua Lowe

Juniper Architecture

ArchitectC34764
Kris Wallace Johnson

Gfds Engineers

EngineerS 4319
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202507150816 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record