1948 Great Hy
San Francisco permit 202507150816 · Sunset/Parkside
New 374sf studio converted into adu on g/f of (e) duplex - under state adu. legalize (e) kitchen and bathroom, no layout changes. no exterior changes.
- Filed
- Aug 20, 2025
- Issued
- Jan 20, 2026 (5 months after filing)
- Completed
- Oct 16, 2026 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 23 stops across 6 departments
- Comments issued
- 5 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 1, 2025 | Aug 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 20, 2025 | Aug 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 20, 2025 | Sep 15, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 20, 2025 | Sep 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2025 | Aug 28, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2025 | Aug 29, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 20, 2025 | Sep 8, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2025 | Aug 21, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 20, 2025 | Sep 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2025 | Sep 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 20, 2025 | Dec 10, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Aug 27, 2025 | Aug 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 19, 2025 | Dec 2, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 19, 2025 | Nov 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 19, 2025 | Nov 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 19, 2025 | Nov 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 19, 2025 | Dec 9, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 19, 2025 | Dec 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 19, 2025 | Dec 1, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Dec 8, 2025 | Dec 8, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 9, 2025 | Dec 9, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Dec 9, 2025 | Dec 9, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 10, 2025 | Jan 20, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $158,976
| Name | Role | License on permit |
|---|---|---|
| Joshua Lowe Juniper Architecture | Architect | C34764 |
| Kris Wallace Johnson Gfds Engineers | Engineer | S 4319 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022