535 Pacific Av #0
San Francisco permit 202507160868 · Chinatown
Bldg structural upgrade to meet 2022 code, include adding steel braces,interior shear walls. strengthening roof diaphragm & steel beams. lowering a section of bldg's basement level to improve accessibility. bldg core restroom upgrade.
- Filed
- Sep 5, 2025
- Issued
- Feb 19, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 11 times, by Permit Center, Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 15, 2025 | Jul 22, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 22, 2025 | Aug 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2025 | Sep 8, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 8, 2025 | Sep 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 8, 2025 | Sep 23, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 8, 2025 | Oct 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2025 | Oct 8, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 8, 2025 | Nov 5, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2025 | Sep 15, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 8, 2025 | Feb 11, 2026 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Oct 14, 2025 | Oct 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Oct 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 19, 2025 | Dec 24, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 19, 2025 | Nov 21, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 25, 2025 | Nov 25, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 3, 2025 | Dec 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2026 | Feb 6, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 4, 2026 | Feb 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2026 | Feb 5, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 6, 2026 | Feb 6, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2026 | Feb 10, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 11, 2026 | Feb 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2026 | Feb 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $15,000,000
| Name | Role | License on permit |
|---|---|---|
| Nuno Machado Lopes Russell + Lopes | Architect | C31066 |
| Kris Wallace Johnson Kris Johnson | Engineer | 4319 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026