1516 Shrader St
San Francisco permit 202507160879 · Inner Sunset
Renovation to (e) ground floor & increase in habitable space which includes an art studio, bedroom & bathroom. demo (e) 95 sf wood deck. rebuild new 68 sf deck. remodel of primary bathroom & addition of bay window at primary bedroom.
- Filed
- Aug 13, 2025
- Issued
- May 11, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 33 stops across 6 departments
- Comments issued
- 10 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 14, 2025 | Aug 14, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jul 15, 2025 | Jul 22, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 14, 2025 | Aug 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 14, 2025 | Sep 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 14, 2025 | Sep 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2025 | Sep 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 14, 2025 | Aug 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 14, 2025 | Aug 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Sep 4, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 14, 2025 | Mar 18, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Sep 24, 2025 | Sep 24, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2025 | Oct 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 12, 2026 | Jan 20, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 14, 2026 | Jan 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 15, 2026 | Jan 15, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2026 | Jan 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2026 | Jan 29, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 16, 2026 | Jan 29, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 23, 2026 | Jan 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 23, 2026 | Mar 4, 2026 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2026 | Feb 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 26, 2026 | Mar 6, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 26, 2026 | Mar 6, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 6, 2026 | Mar 6, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 6, 2026 | Mar 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2026 | Mar 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 11, 2026 | Mar 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2026 | Mar 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2026 | Mar 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 12, 2026 | Mar 12, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 16, 2026 | Mar 16, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 18, 2026 | Mar 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2026 | May 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $372,459
| Name | Role | License on permit |
|---|---|---|
| Emily R Huang Huang Iboshi Architecture | Architect | C26901 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025