3200 Folsom St
San Francisco permit 202507171045 · Bernal Heights
Prepare site for installtion of new pre-fabricated restroom & associate accessibility upgrades. scope includes demolition of (e) site features. installation of new prefabricated restroom and pad and association utilities & pathway improvements. this permit does not include the restroom building
- Filed
- Jul 17, 2025
- Issued
- Oct 9, 2025 (3 months after filing)
- Completed
- Mar 4, 2026 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 9 stops across 5 departments
- Comments issued
- Once, by Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 17, 2025 | Jul 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 17, 2025 | Jul 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 14, 2025 | Aug 14, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 14, 2025 | Aug 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 14, 2025 | Aug 14, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Aug 14, 2025 | Not Applicable |
Public Works disability access review Public Works · PW-DAC | Aug 25, 2025 | Aug 25, 2025 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Sep 22, 2025 | Sep 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 9, 2025 | Oct 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Douglas Zuuring | Engineer | C76818 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025