24 Cortland Av
San Francisco permit 202507221360 · Bernal Heights
New 388 sqft; rear room addition. new electrical and plumbing for washer and dryer. 1/2 bathroom and rear stair access to yard.
- Filed
- Jul 22, 2025
- Issued
- Nov 4, 2025 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 12 stops across 5 departments
- Comments issued
- Once, by Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 22, 2025 | Jul 22, 2025 | Administrative |
Intake Building Inspection · INTAKE | Sep 23, 2025 | Sep 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 23, 2025 | Sep 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2025 | Sep 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2025 | Sep 23, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2025 | Sep 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 26, 2025 | Sep 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 30, 2025 | Sep 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 1, 2025 | Oct 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 1, 2025 | Oct 1, 2025 | Not Applicable |
Development fee collection Building Inspection · DFCU | Nov 4, 2025 | Nov 4, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2025 | Nov 4, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $88,000
| Name | Role | License on permit |
|---|---|---|
| Austin Payne | Engineer | C71212 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025