1200 Carroll Av
San Francisco permit 202507241519 · Bayview Hunters Point
Site permit-2 of 4, fire department training facility, bldg #a1, 2-story, type 2b
- Filed
- Sep 22, 2025
- Issued
- Mar 12, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 89 stops across 7 departments
- Comments issued
- 24 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities, Public Health
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 22, 2025 | Aug 6, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 3, 2025 | Sep 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2025 | Sep 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 22, 2025 | Feb 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 22, 2025 | Oct 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 22, 2025 | Dec 12, 2025 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Sep 22, 2025 | Sep 30, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2025 | Oct 28, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 22, 2025 | Oct 23, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2025 | Oct 6, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 22, 2025 | Oct 8, 2025 | Issued Comments |
Public Health HEALTH-SW | Sep 22, 2025 | Sep 25, 2025 | Approved |
Public Health HEALTH-MH | Sep 22, 2025 | Sep 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 22, 2025 | Mar 2, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2025 | Nov 6, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Oct 31, 2025 | Oct 31, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 21, 2025 | Nov 21, 2025 | Approved-Stipulated |
Public Utilities programs review Public Utilities · SFPUC-PRG | Nov 25, 2025 | Nov 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2025 | Dec 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2026 | Jan 30, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Feb 13, 2026 | Approved-Stipulated |
Public Works disability access review Public Works · PW-DAC | Jan 9, 2026 | Jan 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2026 | Jan 12, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 9, 2026 | Jan 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2026 | Jan 13, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jan 9, 2026 | Jan 16, 2026 | Approved |
Public Health HEALTH-SW | Jan 9, 2026 | Jan 9, 2026 | Approved |
Public Health HEALTH-MH | Jan 9, 2026 | Jan 16, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jan 30, 2026 | Jan 30, 2026 | Approved |
Public Works disability access review Public Works · PW-DAC | Feb 3, 2026 | Feb 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 4, 2026 | Feb 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 4, 2026 | Feb 10, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Feb 4, 2026 | Feb 5, 2026 | Approved |
Public Health HEALTH-MH | Feb 5, 2026 | Feb 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 17, 2026 | Feb 17, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 24, 2026 | Feb 27, 2026 | Approved |
Public Health HEALTH-SW | Feb 24, 2026 | Feb 24, 2026 | Not Applicable |
Development fee collection Building Inspection · DFCU | Mar 2, 2026 | Mar 2, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 2, 2026 | Mar 12, 2026 | Administrative |
Addendum 1: Piles (foundations)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 17, 2026 | Apr 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 6, 2026 | Apr 22, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 22, 2026 | Aug 13, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 22, 2026 | May 14, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Apr 22, 2026 | Jun 8, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2026 | May 21, 2026 | Issued Comments |
Public Health HEALTH-SW | Apr 22, 2026 | May 20, 2026 | Approved |
Public Health HEALTH-MH | Apr 22, 2026 | May 1, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 22, 2026 | Aug 24, 2026 | Administrative |
Public Health HEALTH-MH | Jul 7, 2026 | Jul 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 8, 2026 | Jul 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 18, 2026 | Aug 18, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 18, 2026 | Aug 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2026 | Aug 24, 2026 | Approved |
Public Health HEALTH-SW | Aug 19, 2026 | Aug 24, 2026 | Not Applicable |
Public Health HEALTH-MH | Aug 19, 2026 | Aug 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 24, 2026 | Aug 31, 2026 | Administrative |
Addendum 2: Architectural, structural(superstructural),& mep drawings
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 3, 2026 | Apr 17, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 27, 2026 | Jun 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 15, 2026 | Jun 15, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 15, 2026 | Jun 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 15, 2026 | Jul 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 15, 2026 | Jul 17, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 15, 2026 | Jul 10, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 15, 2026 | Jul 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 15, 2026 | Sep 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 15, 2026 | Jul 8, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 15, 2026 | Jun 17, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 15, 2026 | Jun 22, 2026 | Approved |
Public Health HEALTH-MH | Jun 15, 2026 | Jun 18, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 15, 2026 | In progress | In Progress |
Public Works disability access review Public Works · PW-DAC | Jul 2, 2026 | Jul 21, 2026 | Issued Comments |
Public Health HEALTH-MH | Jul 7, 2026 | Jul 7, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 22, 2026 | In progress | In Progress |
Urban forestry Public Works · DPW-BUF | Aug 12, 2026 | Aug 12, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 27, 2026 | Sep 1, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 7, 2026 | Oct 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 7, 2026 | Oct 19, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 7, 2026 | Oct 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 7, 2026 | Oct 13, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 7, 2026 | Oct 19, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 7, 2026 | Nov 1, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2026 | Oct 7, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 7, 2026 | In progress | — |
Public Works disability access review Public Works · PW-DAC | Oct 7, 2026 | Oct 30, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 7, 2026 | Oct 19, 2026 | Approved |
Public Health HEALTH-MH | Oct 7, 2026 | Oct 7, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $45,000,000
| Name | Role | License on permit |
|---|---|---|
| Thomas Matthew Jasmin Bureau Of Architecture Sfdpw | Architect | C-32761 |
| Raymond Lui Sfdpw | Engineer | S4094 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026