663 44th Av
San Francisco permit 202507251579 · Outer Richmond
Horizontal addition at 1st floor below (e) 2nd floor cantilever to create a new sun room at level 1. convert part of garage to condition space for primary bedroom suite. new windows & doors on the 1st floor level facing the rear yard.
- Filed
- Aug 12, 2025
- Issued
- Feb 12, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 35 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 23, 2025 | Aug 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2025 | Aug 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 12, 2025 | Sep 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 12, 2025 | Sep 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 12, 2025 | Sep 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 12, 2025 | Sep 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 12, 2025 | Aug 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2025 | Aug 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2025 | Aug 14, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 12, 2025 | Feb 5, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Sep 10, 2025 | Sep 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 12, 2025 | Nov 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 12, 2025 | Nov 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 12, 2025 | Nov 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 12, 2025 | Nov 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 12, 2025 | Nov 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2025 | Nov 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2025 | Nov 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 19, 2025 | Nov 19, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Nov 19, 2025 | Nov 19, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 11, 2025 | Dec 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 11, 2025 | Dec 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 11, 2025 | Dec 16, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 11, 2025 | Dec 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 11, 2025 | Dec 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 11, 2025 | Dec 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 11, 2025 | Dec 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 9, 2026 | Jan 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2026 | Jan 20, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 9, 2026 | Jan 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2026 | Jan 12, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Jan 22, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2026 | Jan 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2026 | Jan 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 5, 2026 | Feb 12, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $242,186
| Name | Role | License on permit |
|---|---|---|
| Javier Medina Mark Davis Design | Architect | C34033 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022