1200 Carroll Av
San Francisco permit 202507281703 · Bayview Hunters Point
Site permit-3 of 4, fire department training facility, bldg #b1 & b2, 1-story, type 2b.
- Filed
- Sep 22, 2025
- Issued
- May 15, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 61 stops across 7 departments
- Comments issued
- 15 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 24, 2025 | Aug 6, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 29, 2025 | Sep 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 12, 2025 | Sep 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 22, 2025 | Feb 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 22, 2025 | Oct 30, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 22, 2025 | Dec 8, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2025 | Oct 28, 2025 | Approved-Stipulated |
Public Works disability access review Public Works · PW-DAC | Sep 22, 2025 | Sep 29, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Sep 22, 2025 | Oct 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2025 | Oct 6, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 22, 2025 | Oct 22, 2025 | Approved |
Public Health HEALTH-HM | Sep 22, 2025 | Sep 25, 2025 | Approved |
Public Health HEALTH-SW | Sep 22, 2025 | Sep 25, 2025 | Approved |
Public Health HEALTH-MH | Sep 22, 2025 | Sep 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 22, 2025 | May 8, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2025 | Nov 6, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2025 | Dec 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 27, 2026 | Approved-Stipulated |
Public Works disability access review Public Works · PW-DAC | Jan 13, 2026 | Feb 13, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 2, 2026 | Mar 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 11, 2026 | Mar 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2026 | Apr 13, 2026 | Approved-Stipulated |
Public Works disability access review Public Works · PW-DAC | Mar 25, 2026 | Mar 25, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2026 | Mar 31, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Mar 25, 2026 | Apr 3, 2026 | Approved |
Public Health HEALTH-HM | Mar 25, 2026 | Mar 26, 2026 | Approved |
Public Health HEALTH-SW | Mar 25, 2026 | Mar 31, 2026 | Not Applicable |
Public Health HEALTH-MH | Mar 25, 2026 | Mar 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2026 | Apr 28, 2026 | Approved |
Address verification Building Inspection · ADDR | Apr 30, 2026 | May 1, 2026 | Issued Comments |
Address verification Building Inspection · ADDR | May 7, 2026 | May 7, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | May 7, 2026 | May 8, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 8, 2026 | May 15, 2026 | Administrative |
Addendum 1: Piles
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 28, 2026 | Aug 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 13, 2026 | Aug 13, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 13, 2026 | Sep 10, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 13, 2026 | Sep 22, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Aug 13, 2026 | Aug 25, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 13, 2026 | Aug 24, 2026 | Approved |
Public Health HEALTH-MH | Aug 13, 2026 | Aug 14, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 13, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Sep 22, 2026 | Sep 22, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 2: Structural(superstructure)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 12, 2026 | Aug 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 17, 2026 | Aug 28, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 28, 2026 | Oct 8, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2026 | Oct 8, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Aug 28, 2026 | Sep 16, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2026 | Aug 31, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 28, 2026 | Sep 30, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2026 | Sep 2, 2026 | Not Applicable |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 28, 2026 | Sep 9, 2026 | Not Applicable |
Public Health HEALTH-MH | Aug 28, 2026 | Sep 4, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 28, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Oct 26, 2026 | Oct 27, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Final: architectural,mep,lv & bldg signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 22, 2026 | Nov 2, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $31,378,000
| Name | Role | License on permit |
|---|---|---|
| Michael Bernard Ross Dlr Group Rossdruliscusenbery | Architect | C-18867 |
| Elizabeth Ranieri Kuth Kuth-Rainer Architecture | Architect | C-24316 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026