15 Westgate Dr
San Francisco permit 202507281716 · West of Twin Peaks
2-story horizontal addition in (e) light well south side enlarging kitchen & storage space below. horizontal addition at 3/f over a portion of 2nd story roof will accomodate rebuilding of (e) stair to be code compliant. (e) kitchen will be remodeled.
- Filed
- Sep 16, 2025
- Issued
- Feb 18, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 42 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 24, 2025 | Aug 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2025 | Sep 16, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 16, 2025 | Sep 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 16, 2025 | Oct 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 16, 2025 | Oct 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2025 | Oct 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 16, 2025 | Sep 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 16, 2025 | Sep 17, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 16, 2025 | Sep 30, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 16, 2025 | Jan 12, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Oct 7, 2025 | Oct 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 20, 2025 | Oct 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 5, 2025 | Nov 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 5, 2025 | Nov 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 5, 2025 | Nov 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 5, 2025 | Nov 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 5, 2025 | Nov 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 5, 2025 | Nov 18, 2025 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2025 | Nov 6, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Nov 19, 2025 | Nov 19, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 3, 2025 | Dec 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 3, 2025 | Dec 10, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 3, 2025 | Dec 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 3, 2025 | Dec 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 3, 2025 | Dec 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2025 | Dec 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 3, 2025 | Dec 10, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Dec 10, 2025 | Dec 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 17, 2025 | Dec 22, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 17, 2025 | Dec 22, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 17, 2025 | Dec 18, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 17, 2025 | Dec 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 17, 2025 | Dec 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2025 | Dec 22, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 23, 2025 | Jan 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 23, 2025 | Dec 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 23, 2025 | Dec 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2025 | Dec 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 23, 2025 | Jan 10, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2025 | Dec 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2025 | Dec 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 12, 2026 | Feb 18, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Michael Bernard Harris Michael Harris Architecture | Architect | C15349 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019