San Francisco permit 202507291815 · Presidio Heights

ADUFull plan reviewIssued
Street view · Jun 2025
Google Street View of 750 Presidio Av #0, Jun 2025
Scope of work
As written on the permit application.

Per california government code 65852.2, turn part of garage and storage area into 3 new adus, new laundry room, reduced storage area w/ new toilet room.

Timeline
Key dates from the city record.
Filed
Sep 5, 2025
Issued
Mar 11, 2026 (6 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
8 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 11, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 5, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Sep 8, 2025Administrative

Zoning review

Planning · CP-ZOC

Sep 24, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Sep 15, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 19, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 19, 2025Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Sep 10, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 8, 2025Approved

Urban forestry

Public Works · DPW-BUF

Sep 29, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 11, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jan 7, 2026Administrative

Zoning review

Planning · CP-ZOC

Oct 6, 2025Approved

Zoning review

Planning · CP-ZOC

Nov 17, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 21, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 25, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 24, 2025Approved

Fire Department housing review

Fire Department · SFFD-HQ

Nov 13, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 17, 2025Approved

Urban forestry

Public Works · DPW-BUF

Nov 25, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 17, 2025Approved

Zoning review

Planning · CP-ZOC

Dec 30, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 31, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jan 7, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 23, 2025Approved

Fire Department housing review

Fire Department · SFFD-HQ

Dec 23, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Dec 23, 2025Approved

Urban forestry

Public Works · DPW-BUF

Dec 30, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 23, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Jan 7, 2026Approved

Development fee collection

Building Inspection · DFCU

Jan 7, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Mar 11, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$848,031
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jorge R Carbonell

Jorge Carbonell Architecture

ArchitectC-30680
Michael Austin Hom

Hom & Pisano Engineering Inc.

Engineer71450
Sources