To erect 10 stories, no basement, type i-a, 107 units (100% affordable housing). (r-2, a-3, s-2)
- Filed
- Aug 6, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 26 stops across 7 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works, Public Utilities, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 26, 2025 | Aug 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 29, 2025 | Aug 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 6, 2025 | Aug 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 6, 2025 | Aug 25, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 6, 2025 | Aug 21, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2025 | Aug 14, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 6, 2025 | Sep 12, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2025 | Aug 11, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 6, 2025 | Aug 12, 2025 | Approved |
Public Health HEALTH-HM | Aug 6, 2025 | Aug 6, 2025 | Approved |
Public Health HEALTH-MH | Aug 6, 2025 | Aug 7, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 6, 2025 | In progress | — |
Building plan review Building Inspection · BLDG | Oct 19, 2025 | In progress | In Progress |
Address verification Building Inspection · ADDR | Apr 23, 2026 | Oct 9, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Oct 19, 2026 | Oct 27, 2026 | Approved |
Public Health HEALTH-MH | Oct 19, 2026 | Nov 2, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 21, 2026 | Oct 21, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 22, 2026 | Oct 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 22, 2026 | Oct 22, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 23, 2026 | Oct 23, 2026 | Approved |
Zoning review Planning · CP-ZOC | Nov 2, 2026 | Nov 2, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Filed
- Estimated cost
- $58,874,000
| Name | Role | License on permit |
|---|---|---|
| Joseph Mccue Luk And Associates | Engineer | C74959 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025