Add 1 bed, 1 bath, 371 sq. ft unit per density at ground floor. add 2 bed, 1 bath, 490 sq. ft. adu per ca state program at ground floor. 151 sq. ft. added conditioned space at ground flooor.

Timeline
Key dates from the city record.
Filed
Aug 12, 2025
Issued
May 13, 2026 (9 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
33 stops across 6 departments
Comments issued
6 times, by Planning, Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 12, 2025Administrative

Zoning review

Planning · CP-ZOC

Aug 22, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Sep 11, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 4, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 8, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 14, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 14, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Sep 29, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 14, 2025Approved

Permit Processing Center

Building Inspection · PPC

Oct 31, 2025Administrative

Street use and mapping

Public Works · DPW-BSM

Sep 3, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Sep 10, 2025Approved

Zoning review

Planning · CP-ZOC

Oct 17, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 14, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 9, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 3, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 29, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Oct 1, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 2, 2025Approved

Urban forestry

Public Works · DPW-BUF

Oct 2, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Oct 14, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 21, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 21, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Oct 21, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Oct 27, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 22, 2025Approved

Fire prevention review

Fire Department · SFFD

Oct 30, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Oct 22, 2025Approved

Urban forestry

Public Works · DPW-BUF

Oct 28, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 22, 2025Approved

Development fee collection

Building Inspection · DFCU

Oct 31, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

May 13, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$225,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Colm O Suilleabhain

Benchmark Engineering

EngineerC93697
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202507291847 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record