CheckMyDesigner

1200 Carroll Av

San Francisco permit 202507301913 · Bayview Hunters Point

New buildingFull plan reviewIssued
Street view · Sep 2026
Google Street View of 1200 Carroll Av, Sep 2026
Scope of work
As written on the permit application.

Site permit-4 of 4, fire department training facility, bldg #c1, c2, c3, c4, c5, c6, and c7, 7-story, type 2b.

Timeline
Key dates from the city record.
Filed
Aug 14, 2025
Issued
Apr 3, 2026 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
61 stops across 7 departments
Comments issued
12 times, by Building Inspection, Fire Department, Public Works, Permit Center

Main permit

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 6, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 14, 2025Administrative

Zoning review

Planning · CP-ZOC

Feb 24, 2026Approved

Building plan review

Building Inspection · BLDG

Sep 17, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 24, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 21, 2025Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Sep 23, 2025Approved-Stipulated

Public Health

HEALTH-HM

Aug 15, 2025Approved

Public Health

HEALTH-SW

Aug 18, 2025Approved

Public Health

HEALTH-MH

Aug 18, 2025Approved

Permit Processing Center

Building Inspection · PPC

Mar 11, 2026Administrative

Public Works disability access review

Public Works · PW-DAC

Sep 11, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 17, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 5, 2026Approved

Building plan review

Building Inspection · BLDG

Dec 29, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jan 12, 2026Approved-Stipulated

Public Works disability access review

Public Works · PW-DAC

Jan 15, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jan 26, 2026Approved-Stipulated

Public Health

HEALTH-SW

Jan 14, 2026Approved

Public Health

HEALTH-HM

Jan 15, 2026Approved

Public Health

HEALTH-MH

Jan 16, 2026Approved

Urban forestry

Public Works · DPW-BUF

Mar 2, 2026Approved

Development fee collection

Building Inspection · DFCU

Mar 2, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 3, 2026Administrative

Addendum 1: Piles / foundation

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 26, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jul 20, 2026Administrative

Zoning review

Planning · CP-ZOC

Aug 3, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 25, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 24, 2026Administrative

Fire prevention review

Fire Department · SFFD

Aug 26, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Jul 30, 2026Issued Comments

Public Health

HEALTH-SW

Jul 22, 2026Not Applicable

Public Health

HEALTH-MH

Jul 24, 2026Approved

Permit Processing Center

Building Inspection · PPC

In progress—

Street use and mapping

Public Works · DPW-BSM

Aug 24, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 25, 2026Not Applicable

Building plan review

Building Inspection · BLDG

Oct 26, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Oct 26, 2026Issued Comments

Zoning review

Planning · CP-ZOC

Oct 29, 2026Approved

Building plan review

Building Inspection · BLDG

Oct 29, 2026Approved

Fire prevention review

Fire Department · SFFD

Nov 4, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Oct 29, 2026Approved

Public Health

HEALTH-MH

Nov 3, 2026Approved

Central Permit Bureau

Building Inspection · CPB

In progress—

Addendum 2: Architectureal, structural, mep, lv and building signage.

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 7, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Aug 13, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Aug 14, 2026Administrative

Building plan review

Building Inspection · BLDG

Sep 14, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 15, 2026Not Applicable

Electrical plan review

Building Inspection · MECH-E

Aug 19, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 14, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 24, 2026Approved

Urban forestry

Public Works · DPW-BUF

Sep 16, 2026Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Sep 2, 2026Not Applicable

Public Health

HEALTH-MH

Aug 21, 2026Approved

Permit Processing Center

Building Inspection · PPC

In progressIn Progress

Public Works disability access review

Public Works · PW-DAC

In progress—

Building plan review

Building Inspection · BLDG

In progress—

Electrical plan review

Building Inspection · MECH-E

In progress—

Fire prevention review

Fire Department · SFFD

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Issued
Estimated cost
$34,564,600
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael Bernard Ross

Dlr Group Rossdruliscusenbery

ArchitectC-18867
Elizabeth Ranieri Kuth

Kuth-Rainer Architecture

ArchitectC-24316
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202507301913 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record