1006 Carolina St
San Francisco permit 202507301924 · Potrero Hill
Reconfiguration of lower unit interior- 1/f and 2/f, reconfiguration of upper unit interior- 3/f. removal of (e) rear decks and addition of (n) cantilevered deck @ 3/f. front and rear facade alteration. addition of (n) exterior staris connecting (e) rear yard to ground flr. reroofing.
- Filed
- Aug 13, 2025
- Issued
- Feb 19, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 23 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 28, 2025 | Aug 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2025 | Aug 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 14, 2025 | Oct 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 14, 2025 | Sep 17, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 14, 2025 | Sep 12, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2025 | Sep 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 14, 2025 | Aug 15, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Aug 14, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 14, 2025 | Feb 6, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 24, 2025 | Oct 2, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 1, 2025 | Jan 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 1, 2025 | Dec 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 1, 2025 | Dec 2, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 1, 2025 | Dec 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 1, 2025 | Dec 1, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2025 | Dec 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 27, 2026 | Jan 28, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 29, 2026 | Feb 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2026 | Jan 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 29, 2026 | Feb 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2026 | Jan 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 5, 2026 | Feb 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2026 | Feb 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $770,648
| Name | Role | License on permit |
|---|---|---|
| Daniel Blau Spiegel Saw//Spiegel Ahara Workshop | Architect | C34488 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022