San Francisco permit 202507301936 · Bernal Heights
1) restore building after fire including a 4th floor verical addition and rear addition.2) extend/repair front entry and steps.3) abate complaint 2019-013357enf.4) deferred submittals: sprinklers (nfpa 13) and fire alarm (separate permit).
- Filed
- Oct 27, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 32 stops across 7 departments
- Comments issued
- 14 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 29, 2025 | Aug 6, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 10, 2025 | Oct 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2025 | Oct 29, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 29, 2025 | Oct 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 29, 2025 | Dec 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 29, 2025 | Dec 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 29, 2025 | Nov 20, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 29, 2025 | Jan 4, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2025 | Nov 4, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 29, 2025 | Nov 26, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 29, 2025 | Nov 20, 2025 | Approved |
Public Health HEALTH-MH | Oct 29, 2025 | Oct 31, 2025 | Not Applicable |
Building inspector Building Inspection · BID-INSP | Oct 29, 2025 | In progress | — |
Permit Processing Center Building Inspection · PPC | Oct 29, 2025 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Dec 2, 2025 | Dec 2, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 3, 2026 | Feb 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 5, 2026 | Feb 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Mar 2, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2026 | Feb 11, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Feb 17, 2026 | Feb 24, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 6, 2026 | Jul 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 2, 2026 | Sep 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 2, 2026 | Sep 24, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2026 | Sep 15, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2026 | Sep 15, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 23, 2026 | Sep 23, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 5, 2026 | Oct 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Dawn Ma Q Architecture | Engineer | C64315 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019