104 11th Av
San Francisco permit 202507301951 · Inner Richmond
Horizontal addition on all three floors. build a new foundation throughout and lower garage level 1'-0" replace all exterior doors and windows. interior remodel throughout. new 150 sqft rear deck.
- Filed
- Aug 14, 2025
- Issued
- Nov 7, 2025 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 30 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 30, 2025 | Jul 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 31, 2025 | Jul 31, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2025 | Jul 31, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 31, 2025 | Jul 31, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 4, 2025 | Aug 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2025 | Aug 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 14, 2025 | Oct 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 14, 2025 | Sep 19, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 14, 2025 | Sep 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2025 | Sep 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 14, 2025 | Aug 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 14, 2025 | Aug 19, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 14, 2025 | Sep 16, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Aug 25, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 14, 2025 | Nov 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 6, 2025 | Oct 23, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 6, 2025 | Oct 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2025 | Oct 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 6, 2025 | Oct 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 6, 2025 | Oct 8, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 6, 2025 | Oct 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 6, 2025 | Oct 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 14, 2025 | Oct 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2025 | Oct 22, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 22, 2025 | Oct 23, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 23, 2025 | Oct 28, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 23, 2025 | Nov 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2025 | Oct 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 27, 2025 | Nov 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 6, 2025 | Nov 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $900,000
| Name | Role | License on permit |
|---|---|---|
| Lawson Willard Lawson Willard Architecture | Architect | C26756 |
| Robert Eric Smith Smithworks Engineering | Engineer | S5679 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020