323 Byxbee St
San Francisco permit 202508012174 · Oceanview/Merced/Ingleside
Comply w/ nov #202431941 & nov #202534571: new adu unit "studio" at g/f per state adu program. removal of unpermitted exterior staircase enclosure at rear. removal of unpermitted deck at 2/f.
| Fact | Before | After |
|---|---|---|
| Use | 1 family dwelling | 2 family dwelling |
| Units | 1 | 2 |
| Stories | 2 | No change |
- Filed
- Aug 14, 2025
- Issued
- Jan 26, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 28 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 29, 2025 | Aug 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2025 | Aug 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 14, 2025 | Aug 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 14, 2025 | Sep 4, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 14, 2025 | Sep 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2025 | Sep 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 14, 2025 | Aug 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 14, 2025 | Aug 19, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 14, 2025 | Sep 22, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Aug 25, 2025 | Approved |
Building inspector Building Inspection · BID-INSP | Aug 14, 2025 | Oct 6, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 14, 2025 | Jan 14, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 14, 2025 | Oct 15, 2025 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2025 | Oct 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 20, 2025 | Oct 20, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 12, 2025 | Nov 12, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2025 | Nov 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 19, 2025 | Nov 19, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Nov 20, 2025 | Nov 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 25, 2025 | Nov 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 1, 2025 | Dec 1, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 1, 2025 | Dec 1, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2025 | Dec 4, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 3, 2025 | Dec 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2025 | Dec 11, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Dec 10, 2025 | Dec 10, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Jan 14, 2026 | Jan 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2026 | Jan 26, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $56,500
- Cost after review
- $200,000254% higher
| Name | Role | License on permit |
|---|---|---|
| Wing Kin Lee Wing Lee Architects | Architect | C28929 |
| Lou Xiao Lx Engineering | Engineer | S5130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022