1406 Diamond St
San Francisco permit 202508042218 · Noe Valley
3/f vertical addition. 1/f: (n) entry.2/f: interior renovations (dining/living). (n) 3/f: 2 beds, 1 bath, 1 sitting rm. new int stairs connect 1/2/3. rear yd: new site stair connection 1/f to 2/f rear yard.
- Filed
- Aug 19, 2025
- Issued
- Jun 30, 2026 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 1, 2025 | Aug 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2025 | Aug 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 20, 2025 | Sep 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2025 | Sep 26, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2025 | Sep 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2025 | Sep 18, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 20, 2025 | Aug 21, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2025 | Aug 21, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 20, 2025 | Oct 6, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2025 | Aug 25, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 20, 2025 | Jun 24, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Sep 26, 2025 | Sep 26, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 28, 2026 | Feb 6, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 29, 2026 | Jan 29, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2026 | Jan 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 3, 2026 | Feb 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 4, 2026 | Feb 4, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 10, 2026 | Mar 4, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2026 | Feb 19, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Feb 17, 2026 | Feb 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 6, 2026 | May 5, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2026 | Apr 16, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2026 | Apr 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2026 | Apr 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2026 | Apr 24, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | May 5, 2026 | May 5, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 5, 2026 | May 18, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 22, 2026 | May 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 27, 2026 | Jun 1, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | May 28, 2026 | May 28, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 1, 2026 | Jun 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2026 | Jun 2, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 12, 2026 | Jun 18, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 18, 2026 | Jun 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2026 | Jun 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2026 | Jun 22, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 24, 2026 | Jun 30, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | Jun 26, 2026 | Jun 26, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $435,078
| Name | Role | License on permit |
|---|---|---|
| Sven Erik Lavine Sven Lavine Architecture | Architect | C30122 |
| Sean Thomas Condry Stc Design & Engineering | Engineer | C60860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022