371 A Ellington Av
San Francisco permit 202508052322 · Outer Mission
Addition of a new adu on the 1st fl in acordance with govement code section 6582.2 construction of anew laundry room on the 2nd floor.construction of a 2nd floor deck to access to the rear yard.
- Filed
- Aug 12, 2025
- Issued
- Nov 12, 2025 (3 months after filing)
- Completed
- Jun 22, 2026 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 30, 2025 | Aug 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2025 | Aug 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 13, 2025 | Aug 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2025 | Sep 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 13, 2025 | Sep 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 13, 2025 | Sep 12, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 13, 2025 | Aug 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 13, 2025 | Aug 14, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 13, 2025 | Aug 25, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 13, 2025 | Aug 19, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 13, 2025 | Oct 30, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2025 | Sep 24, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Sep 23, 2025 | Sep 23, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Sep 23, 2025 | Oct 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 30, 2025 | Sep 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 30, 2025 | Sep 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2025 | Oct 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 14, 2025 | Oct 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 16, 2025 | Oct 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2025 | Oct 20, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 16, 2025 | Oct 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2025 | Oct 22, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 16, 2025 | Oct 20, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2025 | Oct 17, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 16, 2025 | Oct 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2025 | Oct 21, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 20, 2025 | Oct 20, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 27, 2025 | Oct 27, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 29, 2025 | Oct 29, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Oct 29, 2025 | Oct 29, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2025 | Nov 12, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Junjian Lao Lao Engineering | Engineer | C82114 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011