3864 25th St
San Francisco permit 202508052366 · Noe Valley
New 2 car garage, new spiral staircase from garage level to /from existing first flr. planning app# 2024-003281prj; 2024-003281 var; 2024-003281 hrr historic resource reiew.
- Filed
- Aug 5, 2025
- Issued
- Sep 15, 2026 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Twice, by Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 5, 2025 | Aug 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 12, 2025 | Aug 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2025 | Aug 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2025 | Aug 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 17, 2025 | Nov 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 17, 2025 | Nov 17, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 11, 2025 | Dec 12, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2026 | Sep 14, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 14, 2026 | Sep 14, 2026 | Not Applicable |
Urban forestry Public Works · DPW-BUF | Sep 14, 2026 | Sep 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 15, 2026 | Sep 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $265,000
| Name | Role | License on permit |
|---|---|---|
| Rajat Randev Rajat Randev | Architect | C-37339 |
| Fareed A Himmati Himmati Engineering Inc. | Engineer | 58011 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2014