1640 Scott St
San Francisco permit 202508062454 · Japantown
Build new elevator pit & hoistway for a machine roomless, gurney-size service elevator (by others). to accomodate the elevator, demolish & rebuild general restroom & accessible guest room/bathroom @ 1st floor. remove 1 guest room/bathroom & replace with office/lounge room @ 2nd floor & remove
- Filed
- Aug 20, 2025
- Issued
- Nov 20, 2025 (3 months after filing)
- Completed
- Not completed yet
- Review stops
- 20 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 4, 2025 | Aug 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2025 | Aug 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 21, 2025 | Aug 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 21, 2025 | Sep 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 21, 2025 | Sep 24, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 21, 2025 | Oct 26, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2025 | Aug 26, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 21, 2025 | Nov 18, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Sep 18, 2025 | Sep 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 29, 2025 | Oct 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 29, 2025 | Nov 6, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 29, 2025 | Nov 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 29, 2025 | Oct 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 29, 2025 | Nov 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 10, 2025 | Nov 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 12, 2025 | Nov 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 12, 2025 | Nov 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 12, 2025 | Nov 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 12, 2025 | Nov 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2025 | Nov 20, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $850,000
| Name | Role | License on permit |
|---|---|---|
| Karin Louise Payson Karin Payson Architecture | Architect | C22856 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026