4179 A 26th St
San Francisco permit 202508062456 · Noe Valley
To erect 1 story, no basement, type v-b, detached adu. 02 sep '25 - travels with p/a: 2025-0815-3192. efm.
- Filed
- Aug 26, 2025
- Issued
- Mar 10, 2026 (6 months after filing)
- Completed
- Aug 18, 2026 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 51 stops across 6 departments
- Comments issued
- 13 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 1, 2025 | Aug 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2025 | Aug 27, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 27, 2025 | Oct 7, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 27, 2025 | Sep 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 27, 2025 | Sep 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 27, 2025 | Sep 5, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 27, 2025 | Sep 2, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 27, 2025 | Sep 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 27, 2025 | Oct 6, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 27, 2025 | Aug 28, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 27, 2025 | Sep 11, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Aug 27, 2025 | Mar 3, 2026 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Sep 5, 2025 | Sep 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2025 | Sep 19, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 26, 2025 | Sep 26, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Oct 3, 2025 | Oct 3, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Oct 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2025 | Dec 4, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 28, 2025 | Nov 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2025 | Nov 21, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 28, 2025 | Oct 28, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2025 | Oct 29, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 28, 2025 | Nov 10, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2025 | Oct 29, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 28, 2025 | Nov 7, 2025 | Not Applicable |
Zoning review Planning · CP-ZOC | Dec 3, 2025 | Dec 5, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 3, 2025 | Jan 8, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 3, 2025 | Dec 9, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Dec 3, 2025 | Dec 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2025 | Dec 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 3, 2025 | Dec 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 3, 2025 | Dec 4, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Jan 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 14, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Jan 23, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Jan 21, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jan 13, 2026 | Jan 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2026 | Jan 14, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 13, 2026 | Jan 26, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Jan 15, 2026 | Approved |
Building Inspection PAD-STR-QC | Jan 29, 2026 | Jan 29, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | Jan 29, 2026 | Jan 30, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 10, 2026 | Feb 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Feb 12, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 10, 2026 | Feb 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2026 | Feb 12, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Feb 10, 2026 | Feb 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2026 | Feb 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 10, 2026 | Mar 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Feb 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Mar 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $151,587
| Name | Role | License on permit |
|---|---|---|
| Venkata Rohit Grandhi Venkata Rohit Grandhi, P.E. | Engineer | C88709 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025