639 Teresita Bl
San Francisco permit 202508072519 · West of Twin Peaks
Remove dryrot ground level deck and rebuild rear dekc and stairs in kind.demolish existing rear wood balconies on 1st and 2nd flrs.install new metal balconies on rear elevations legalize exist.first basement as media room w/bathroom fully sprinkler entire bldg.deferred permit:sprinkler entire bldg
- Filed
- Dec 5, 2025
- Issued
- Feb 25, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Permit Center
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 7, 2025 | Aug 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 7, 2025 | Aug 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Aug 8, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 16, 2025 | Oct 6, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 12, 2025 | Dec 1, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 5, 2025 | Dec 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 5, 2025 | Dec 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 5, 2025 | Dec 30, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 5, 2025 | Dec 29, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2025 | Jan 2, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 5, 2025 | Dec 11, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2025 | Dec 19, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 5, 2025 | Feb 9, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 21, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 22, 2026 | Jan 22, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 27, 2026 | Jan 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 27, 2026 | Jan 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 27, 2026 | Jan 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 27, 2026 | Feb 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 27, 2026 | Jan 28, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 27, 2026 | Jan 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 9, 2026 | Feb 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $143,164
| Name | Role | License on permit |
|---|---|---|
| Samuel Kwong Arcus Architecture & Planning | Architect | C14679 |
| Edmond Wong | Engineer | C86522 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019