403 Judah St
San Francisco permit 202508082628 · Inner Sunset
Prop h: change of use at g/f to childcare facility -add children ada restroom, food prep/laundry area, activity area & playground,install plumbing, electrical, hvac, floor & wall finishes. deferred structural submittal for outdoor patio. (dbi addressing will issue new address: 403 judah st)
- Filed
- Aug 22, 2025
- Issued
- Apr 15, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 38 stops across 5 departments
- Comments issued
- 13 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 21, 2025 | Aug 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 22, 2025 | Aug 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 22, 2025 | Mar 31, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 9, 2025 | Sep 24, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2025 | Sep 10, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 10, 2025 | Sep 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 10, 2025 | Sep 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 10, 2025 | Sep 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 10, 2025 | Sep 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2025 | Nov 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2025 | Nov 21, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 21, 2025 | Nov 21, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2025 | Nov 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2025 | Nov 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 24, 2025 | Nov 24, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 26, 2025 | Nov 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 26, 2025 | Dec 1, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 26, 2025 | Dec 3, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 1, 2025 | Dec 1, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 1, 2025 | Dec 1, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2025 | Dec 2, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2025 | Dec 4, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 10, 2025 | Dec 10, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 9, 2026 | Feb 9, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2026 | Feb 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 10, 2026 | Feb 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 11, 2026 | Feb 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 11, 2026 | Feb 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2026 | Feb 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 17, 2026 | Feb 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 25, 2026 | Mar 25, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 25, 2026 | Mar 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2026 | Mar 25, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2026 | Mar 30, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2026 | Mar 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 26, 2026 | Mar 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 30, 2026 | Mar 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2026 | Apr 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $327,000
| Name | Role | License on permit |
|---|---|---|
| Sy-Cheng Tsai Rcusa Corp | Architect | C24234 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026