Prop h: change of use (e) b occupany bldg to proposed a occupancy. new elevator & sprinklers proposed under separate permits. new restrooms & modify (e) restrooms. modify stair well & demising walls per plan. installation of beverage service bars & walk-in refridgerator. no food program/kitchen.
- Filed
- Aug 8, 2025
- Issued
- Mar 4, 2026 (7 months after filing)
- Completed
- Oct 30, 2026 (8 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 49 stops across 6 departments
- Comments issued
- 15 times, by Building Inspection, Public Works, Public Health, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 8, 2025 | Aug 8, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Sep 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2025 | Aug 14, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 8, 2025 | Aug 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 8, 2025 | Aug 12, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 8, 2025 | Mar 2, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2025 | Aug 11, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Aug 13, 2025 | Aug 13, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Aug 13, 2025 | Aug 13, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 20, 2025 | Aug 20, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 22, 2025 | Aug 22, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 4, 2025 | Sep 4, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 10, 2025 | Nov 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 10, 2025 | Nov 14, 2025 | In Progress |
Structural plan approval Building Inspection · PAD-STR | Nov 10, 2025 | Jan 30, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2025 | Nov 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2025 | Nov 17, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Nov 12, 2025 | Nov 13, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2025 | Nov 13, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 13, 2025 | Nov 13, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Nov 14, 2025 | Nov 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 20, 2025 | Nov 20, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2025 | Dec 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 17, 2025 | Dec 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 17, 2025 | Dec 22, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 22, 2025 | Dec 22, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 23, 2025 | Dec 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2025 | Dec 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2025 | Dec 23, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Dec 24, 2025 | Dec 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 29, 2025 | Dec 29, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 23, 2026 | Jan 23, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 23, 2026 | Jan 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 26, 2026 | Jan 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 26, 2026 | Jan 26, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2026 | Jan 28, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Jan 27, 2026 | Jan 27, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 2, 2026 | Feb 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2026 | Feb 2, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 23, 2026 | Feb 23, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 23, 2026 | Feb 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2026 | Feb 24, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 24, 2026 | Feb 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2026 | Feb 24, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Feb 24, 2026 | Feb 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 25, 2026 | Feb 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 25, 2026 | Feb 25, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2026 | Feb 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 2, 2026 | Mar 4, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $2,088,072
| Name | Role | License on permit |
|---|---|---|
| Jason Allen Pisano Hom-Pisano Engineering Inc | Engineer | C69708 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026