475 Pine St
San Francisco permit 202508112709 · Financial District/South Beach
Replace existing type 2 cooking hood with new type 1 hood at (e) restaurant. new kitchen cooking equipment. minor finishes repairs and replacement food service equipment. no structural work. new mechanical, electrical/plumbing (mep) work.
- Filed
- Aug 11, 2025
- Issued
- Oct 1, 2025 (2 months after filing)
- Completed
- Feb 10, 2026 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- Twice, by Building Inspection, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 11, 2025 | Aug 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 11, 2025 | Aug 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 11, 2025 | Aug 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2025 | Aug 11, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 11, 2025 | Aug 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2025 | Aug 11, 2025 | Approved |
Public health review Public Health · HEALTH | Aug 11, 2025 | Aug 11, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Aug 22, 2025 | Aug 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 5, 2025 | Sep 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2025 | Oct 1, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $25,000
| Name | Role | License on permit |
|---|---|---|
| Michael Steiner Steiner Architects | Architect | C31950 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2019