67 Blake St
San Francisco permit 202508122793 · Presidio Heights
Two units: level 1 177 sf addition, new bedroom, bath, storage, lower foundation, new windows & doors. level 2: 32 sf addition, interior remodel, new rear deck in-kind, new windows & doors, new stair to level 1, replace front stair in-kind. level 3:32 sf addition, inter remodel, new rear yard deck,
- Filed
- Aug 12, 2025
- Issued
- Sep 11, 2025 (1 month after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 12, 2025 | Aug 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 12, 2025 | Aug 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 12, 2025 | Aug 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 12, 2025 | Aug 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 12, 2025 | Aug 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2025 | Aug 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 28, 2025 | Aug 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2025 | Aug 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2025 | Aug 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2025 | Sep 11, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $593,365
| Name | Role | License on permit |
|---|---|---|
| Michael Storer | Engineer | C-84865 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025