Rev 202410293938: structural field changes, minor interior layout changes and expand basement addition (548sf) including new mechanical room.

Timeline
Key dates from the city record.
Filed
Jan 6, 2026
Issued
May 12, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 7 departments
Comments issued
5 times, by Permit Center, Planning, Building Inspection, Public Works
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Aug 12, 2025Administrative

Zoning review

Planning · CP-ZOC

Nov 4, 2025Approved

Permit Center

Permit Center · PERMIT-CTR

Dec 2, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jan 5, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jan 7, 2026Administrative

Zoning review

Planning · CP-ZOC

Jan 9, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Feb 27, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 28, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 22, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jan 8, 2026Approved

Urban forestry

Public Works · DPW-BUF

Feb 9, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 9, 2026Approved

Public Health

HEALTH-MH

Jan 8, 2026Approved

Permit Processing Center

Building Inspection · PPC

May 11, 2026Administrative

Building plan review

Building Inspection · BLDG

Mar 31, 2026Approved

Zoning review

Planning · CP-ZOC

Mar 12, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 3, 2026Approved

Fire prevention review

Fire Department · SFFD

May 7, 2026Approved

Street use and mapping

Public Works · DPW-BSM

May 4, 2026Approved

Urban forestry

Public Works · DPW-BUF

May 1, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 4, 2026Approved

Public Health

HEALTH-MH

May 5, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 12, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$75,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Richard Doyle Beard

Richard Beard Architect

ArchitectC-12947
David M Strandberg

Strandberg Engineering

Engineer62993
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202508122863 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record