436 Eureka St
San Francisco permit 202508143077 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Altered site permit (ref 2018-10009-2526) to allow for the expansion of the basement, add a sky light, and change windows sizes.this set is still in conformance with the board of appeals decision (appeal #22-013) and the subsequent boa permit #2022-0527-2182.
- Filed
- Aug 21, 2025
- Issued
- Nov 10, 2025 (3 months after filing)
- Completed
- Not completed yet
- Review stops
- 42 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Public Works, Public Utilities, Fire Department
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 7, 2025 | Aug 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2025 | Aug 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 21, 2025 | Aug 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 21, 2025 | Sep 23, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 21, 2025 | Sep 24, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2025 | Sep 17, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 21, 2025 | Oct 7, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2025 | Aug 28, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 21, 2025 | Nov 6, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2025 | Sep 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 17, 2025 | Oct 17, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 17, 2025 | Oct 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 27, 2025 | Oct 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 27, 2025 | Oct 27, 2025 | Not Applicable |
Urban forestry Public Works · DPW-BUF | Oct 28, 2025 | Oct 28, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 30, 2025 | Oct 30, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Oct 31, 2025 | Oct 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 31, 2025 | Nov 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2025 | Nov 5, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 31, 2025 | Nov 5, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2025 | Nov 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 6, 2025 | Nov 10, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 10, 2025 | Nov 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 19, 2025 | Nov 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 20, 2025 | Apr 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Nov 20, 2025 | Jan 2, 2026 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Nov 20, 2025 | Jan 2, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2025 | Dec 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 20, 2025 | Dec 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2025 | May 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2025 | Dec 2, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 20, 2025 | May 8, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 10, 2025 | Dec 10, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 4, 2026 | Mar 4, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 4, 2026 | Mar 4, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2026 | Apr 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 6, 2026 | Apr 6, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 22, 2026 | Apr 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 22, 2026 | May 7, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2026 | Apr 28, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 4, 2026 | May 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 8, 2026 | May 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Nicholas C Thomas Thomas Works A+D | Architect | C38546 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023